Typical timelines by project type
| Project | Typical timeline | What drives it |
|---|---|---|
| Landing page | 3–10 days | Copy ready? Integrations with ads and CRM |
| Small business site (5–10 pages) | 2–5 weeks | Content, design rounds, number of templates |
| WordPress site with custom design | 3–6 weeks | Custom blocks, editor training |
| E-commerce store | 4–10 weeks | Product data, payments, shipping rules |
| Web application / portal | 2–6 months+ | Features, user roles, integrations, testing |
| Mobile app (iOS + Android) | 2–5 months+ | Features, backend, store review |
Where the time goes
- Discovery and scope (2–5 days): goals, pages, features, budget.
- Design (1–3 weeks): wireframes, then visual design for key pages.
- Build (1–6 weeks for sites, longer for apps).
- Content entry and review.
- Testing on real devices, speed and SEO checks.
- Launch, redirects and monitoring.
The five most common causes of delay
- Content (text, photos, product data) not ready.
- Scope changing mid-build.
- Too many people giving feedback without one decision-maker.
- Third-party access — hosting, domains, payment accounts — arriving late.
- Unclear approval: 'looks good' versus 'approved, please launch'.
How to get your site live faster
Prepare content in parallel with design, name one person who approves each stage, and separate launch must-haves from later improvements. A smaller site that launches in three weeks and grows is usually worth more than a perfect site that launches in three months.